Impact of coronavirus (COVID-19) on contracts

By Farleys Solicitors LLP

24 Mar 2020

stephen-greenwood-3.jpg

We have received many calls about termination of contracts as a result of the coronavirus outbreak.  Unforeseen events do not release contracted parties from their obligations in an agreement unless the contract specifically provides for that in a force majeure clause or if the contract is ‘frustrated’.

Force majeure

Most contracts contain a force majeure clause excusing the parties from performance of their obligations if certain events arise.  ‘Force majeure’ translates from French as ‘superior force’ meaning that something significant has occurred meaning obligations in a contract cannot be performed.  To apply, the clause must specifically cover the event that has arisen.  In the case of coronavirus then a contract that has been recently entered into might specifically give the coronavirus outbreak as a reason for termination.  More likely, is that a force majeure clause might refer to government action, travel difficulties, disease or perhaps a more general reference to unforeseen disruption.  A clause must be carefully considered to check whether it applies in the circumstances.

If a force majeure clause does apply then consideration needs to be given as to whether coronavirus is in fact the cause of the inability to perform obligations, how long the clause excuses the parties from their obligations and what obligations the affected party has to try and mitigate its effect.  A contract will normally have an obligation that any notices are given within a particular time after the unforeseen event occurs and in a particular way so the notice provisions in the contract must be checked and complied with.

Frustration

Even if there is no force majeure clause, parties might be discharged from their obligations if the impact of coronavirus makes it physically or commercially impossible to perform the contract, or would render performance radically different from what the parties contemplated when the contract was made.  An example might be if the government introduced a law making it illegal to undertake an obligation in the contract.

Existing contracts

To seek relief from your obligations in a contract, or if you are the recipient of a notice from another party then the terms of the contract and the circumstances surrounding the request need to be carefully considered.  Failure to perform obligations in contracts may impact other contracts and obligations to third parties and the effect on them could be significant.  Before an issue arises we recommend that you review your contracts and seek our advice on where you stand.  It is possible to agree a variation to a contract to address the change in circumstances or to introduce provisions to cater for possible future impact to save unnecessarily drastic action now.

New contracts

For anyone entering into a new contract, consider what possible impact coronavirus might have on your agreement and an appropriate clause should be inserted to address the consequences.

For further advice on how the coronavirus (COVID-19) will affect your commercial contracts, our commercial team are on hand to help. Call 0845 287 0939 or contact us by email at www.farleys.com/contact-us.

Latest news

1

University of Central Lancashire celebrates hat-trick of wins at Educate North Awards University of Central Lancashire winners at Educate North Award Winners 2025

University of Central Lancashire celebrates hat-trick of wins at Educate North Awards

04 Apr 2025

2

The Villa’s sister venue shuts its doors The Villa Levens and The VillaWrea Green (Image credit: The Villa Levens and The Villa Wrea Green)

The Villa’s sister venue shuts its doors

04 Apr 2025

3

PM urged not to retaliate over tariffs Manufacturing

PM urged not to retaliate over tariffs

03 Apr 2025

4

CMAC Group appoints Matthew Ratcliffe as chief operating officer Matthew Ratcliffe CMAC

CMAC Group appoints Matthew Ratcliffe as chief operating officer

03 Apr 2025

5

For sale signs at The Villa Villa Wrea Green has been brought to market (Image credit: The Villa Wrea Green)

For sale signs at The Villa

02 Apr 2025

Pc Prestonmacan Gif980x120 March
Background image for hub sign up block

LBV Hub

Leverage Lancashire Business View platforms

Post your news
Post your events
Post your offers
Build your network
Improve your SEO
Gain coverage in the magazine
Sign-up
Events
Lancashire Net Zero Carbon Conference
Net Zero Carbon Social 1200px
Networking
18 Jun 2025

Lancashire Net Zero Carbon Conference

Crow Wood Hotel & Spa Resort, Burnley, BB12 0RT

08:30 - 13:00

CMI Level 5 Management and Leadership Course
UCLanAerialCampus.jpg.jpg
LBV Hub Seminars
21 Feb 2025 - 21 Feb 2026

CMI Level 5 Management and Leadership Course

Preston Campus, Preston , PR1 2HE

09:00 - 17:00

CMI Level 5 Project Management Course
UCLanAerialCampus.jpg.jpg
LBV Hub Seminars
21 Feb 2025 - 21 Feb 2026

CMI Level 5 Project Management Course

Preston Campus, Preston, PR1 2HE

08:00 - 17:00

RISE - The Academy for Female Leaders and Managers
WENDY BOWERS RISE Illustrstion copy.jpg.jpg
LBV Hub Seminars
02 Apr 2025 - 08 Oct 2025

RISE - The Academy for Female Leaders and Managers

East Lancashire Chamber of Commerce, Clayton le Moors, BB5 5JR

09:00 - 15:30

The Business Network Central & East Lancashire
LBV Hub Networking
24 Apr 2025 - 24 Apr 2025

The Business Network Central & East Lancashire

Stanley House, Blackburn, BB2 7NP

11:30 - 14:15

People Power: Exclusive Event Series
Stay ahead in 2025.jpg.jpg
LBV Hub Seminars
29 Apr 2025 - 29 Apr 2025

People Power: Exclusive Event Series

People's History Museum, Manchester, M3 3ER

17:00 - 21:00

Planning for the future + navigating Inheritance Tax changes
Planning for the future + navigating Inheritance Tax changes for website.png.png
LBV Hub Seminars
01 May 2025 - 01 May 2025

Planning for the future + navigating Inheritance Tax changes

Stanley House Hotel, Mellor, Blackburn, BB2 7NP, Blackburn, BB2 7NP

08:00 - 10:30

A night at the races
1.png.png
LBV Hub Dinners / Balls
02 May 2025 - 02 May 2025

A night at the races

Morecambe FC, Morecambe, LA4 4TB

19:00 - 23:59

Celebrating 50 years of KTP
UCLanAerialCampus.jpg.jpg
LBV Hub Networking
07 May 2025 - 07 May 2025

Celebrating 50 years of KTP

University of Central Lancashire , Preston, PR1 2HE

16:00 - 18:00

Research and Knowledge Exchange Showcase
13421_research_knowledge_exchange_2025_600x300.jpg.jpg
LBV Hub Awards
07 May 2025 - 08 May 2025

Research and Knowledge Exchange Showcase

University of Central Lancashire , Preston, PR1 2HE

09:00 - 17:00

Innovating business solutions through PhD Partnerships
30478 Skills Bootcamp open day setting.jpg.jpg
LBV Hub Networking
07 May 2025 - 07 May 2025

Innovating business solutions through PhD Partnerships

University of Central Lancashire, Preston , PR1 2HE

14:30 - 15:30

Enhancing Your Workforce with CPD
LBV Hub Networking
08 May 2025 - 08 May 2025

Enhancing Your Workforce with CPD

University of Central Lancashire, Preston, PR1 2HE

13:15 - 14:15

Advertise with us

Reaching 50,000 members, our print, digital and event platforms offer a fantastic way to raise your business profile and help you grow.

Find out more Lbv121 Online Graphic
Subscribe now

Weekly news bulletin